PriceLock is the RealUniverse offering for accountable commitments. It moves the decisions that usually happen in the field to before construction starts, and it keeps the record of who decided what.

PriceLock is the RealUniverse offering for accountable commitments. It moves the decisions that usually happen in the field to before construction starts, and it keeps the record of who decided what.

PriceLock

Homeowner and project professionals reviewing plans together

BEFORE YOU CHOOSE A CONTRACTOR

Their commitment.

Their commitment.

Their accountability.

Their accountability.

Compare the price and completion date. Understand when the contractor owes you $1,000 per day for late completion before you choose.

The accepted terms become part of your PriceLock agreement, together with the agreed conditions and exceptions. Completed work is independently verified, and milestone payments follow the agreement’s verification and release conditions.

01

Price protection starts with the scope

Agree on the complete work and a firm price before signing. Make selections, allowances, and exclusions explicit. Any change to scope, price, or timing follows the agreement’s approval process.

02

Late completion costs the contractor

If your contractor misses the agreed completion date, they owe you $1,000 for each day of late completion. The signed agreement defines when it applies, including approved extensions and exceptions.

03

Daily visibility keeps you informed

Know who is working in your home. See daily updates and photos, the next planned work, and any issue that needs your decision.

Imagine choosing a $200,000 bid and planning your family’s life around a six-week renovation.

Imagine choosing a $200,000 bid and planning your family’s life around a six-week renovation.

ILLUSTRATIVE SCENARIO

THE PROMISE

THE SURPRISE

THE DISRUPTION

When the lowest bid costs more

$200,000

+$56,000

Another month

A bid. A six-week schedule.

Missing scope and added costs.

Your household still on hold.

Then the check clears. Missing scope appears. The date slips. Now you need another $56,000—and another month out of your home.

The lowest bid can become the most expensive promise.

THE SEQUENCE

Define → Align → Secure → Build → Verify → Release → Record

Define → Align → Secure → Build → Verify → Release → Record

01

Define

Your team documents the scope, drawings, selections, and allowances before the project goes out to bid.

02

Align

Agree on the price, schedule, payment milestones, and responsibilities. Late completion carries $1,000 per day owed by the contractor under the agreement.

03

Secure

Fund each labor milestone before it starts and prefund materials separately. Confirm the funding provider and payment conditions.

04

Build

Follow the people, daily progress, photos, and upcoming work. A change needs approval and funding before it proceeds.

05

Verify

An independent inspector checks the milestone against the approved plans and specifications, without seeing project prices.

06

Release

Authorize payments under the agreed rules. Contractor profit and general requirements wait for milestone inspection; approved supplier and trade payments may occur earlier.

07

Record

Keep what was agreed, built, verified, and paid in your Home Record, along with the people, selections, and warranties behind the work.

TWO KINDS OF MONEY

Materials and completed work

Materials and completed work

follow different rules.

follow different rules.

Materials & trade progress

Suppliers can be paid when an order is authorized. For agreed long tasks, subcontractors may receive progress payments of up to 50% before inspection, with the balance afterward. Some tasks may be paid on completion without inspection when defined in advance.

Contractor payment & closeout

Contractor profit, project management, and general requirements release only after milestone inspection. The final 10% is the final walkthrough and punch-list milestone.

Release & confirmation

The designated person separately authorizes payment when the release conditions are met. Record payment confirmation when it occurs.

Three responsibilities, kept separate. The designer reviews design intent and selections. An independent verifier identified in the project agreement checks completed work against the agreed requirements. The authorized person approves payment after the agreed release conditions are satisfied. A design review does not replace verification, and a verification result does not automatically release money; it is the evidence the authorized person relies on.

SEE THE DECISIONS BEHIND THE COMMITMENT

One project.

One project.

Five moments that matter.

Five moments that matter.

See how PriceLock works through a kitchen renovation—from setting the terms to checking work and releasing payment.

KITCHEN RENOVATION

Illustrative example

01

The agreement

02

A deposit

03

A change

04

A quality check

05

Payment release

THE AGREEMENT

Clear commitments from the start.

The agreement records the kitchen scope, price, completion date, and $1,000 per day owed to the homeowner for late completion under its terms.

AGREED PRICE

$200,000

COMPLETION DATE

March 26, 2027

DAILY LATE PENALTY

$1,000 per day

The contractor owes the homeowner $1,000 for each day of late completion, subject to the agreement’s terms.

KITCHEN RENOVATION

Illustrative example

01

The agreement

02

A deposit

03

A change

04

A quality check

05

Payment release

THE AGREEMENT

Clear commitments from the start.

The agreement records the kitchen scope, price, completion date, and $1,000 per day owed to the homeowner for late completion under its terms.

AGREED PRICE

$200,000

COMPLETION DATE

March 26, 2027

DAILY LATE PENALTY

$1,000 per day

The contractor owes the homeowner $1,000 for each day of late completion, subject to the agreement’s terms.

The project scenarios and sample records are illustrative. They explain the PriceLock approach and are not customer results or live product screens.